Projects / North Scotland
Corshellach Battery Energy Storage System
Corshellach Energy Storage Limited at Berryburn 275/33kV GSP Substation
- Connection date
- 31 Oct 2028 +12 months since 14 Aug
- Gate
- Gate 2
- Status
- Consented
- Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-002328
- Tracked since
- 14 Aug 2026
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consented
- 28 Aug 2026 registerConnection date moved from 31 Oct 2027 to 31 Oct 2028 (+12 months)
- 28 Aug 2026 registerGiven a Gate 2 connection offer
Also queued at Berryburn 275/33kV GSP Substation
Substation view2 other projects, 160 MW still to connect at this substation in total.