Corshellach Battery Energy Storage System
Corshellach Energy Storage Limited at Berryburn 275/33kV GSP Substation
- Connection date
- 31 Oct 2028 +12 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 19 Dec 2024
Northumberland, reference 24/01073/APP · Source: REPD - Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-002328
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 28 Aug 2026 registerConnection date moved from 31 Oct 2027 to 31 Oct 2028 (+12 months)
- 28 Aug 2026 registerGiven a Gate 2 connection offer
- 6 Feb 2026 registerConnection point changed from Berry Burn GSP to Berryburn 275/33kV GSP Substation
- 28 Mar 2025 registerCustomer changed from Renewable Energy Systems Limited to Corshellach Energy Storage Limited
- 24 Dec 2024 registerConnection date moved from 31 Oct 2031 to 31 Oct 2027 (−48 months)
- 29 Aug 2023 registerRenamed from Corshellach Batery Energy Storage System
- 30 Jun 2023 registerAdded to the register
Also at Berryburn 275/33kV GSP Substation
Substation view2 other projects, 160 MW still to connect at this substation in total. 43.2 MW is due to connect here before this project’s connection date of 31 Oct 2028.