Ayr 275/33kV
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Ayr Energy Storage | KXP ALPHA I LIMITED | Storage | 150 | 30 Oct 2028 +12 mo | Gate 2 | Consents Approved |
| Clonmacate Farm BESS | GPC Project 11 Ltd | Storage | 200 | 31 Oct 2030 | Not stated | Scoping |
| FPE Ayr BESS | FUTURE POWER ENTERPRISES LTD | Storage | 200 | 30 Oct 2037 | Not stated | Scoping |
| Holmston Farm Battery Energy Storage System | Field Holmston Ltd | Storage | 0 | Connected | Gate 2 | Built |
Recent changes
- Holmston Farm Battery Energy Storage SystemSouth Scotland, Storage49.9 MW now connectedConnected
- Holmston Farm Battery Energy Storage SystemSouth Scotland, StorageStatus changed from Under Construction/Commissioning to Built
- Holmston Farm Battery Energy Storage SystemSouth Scotland, StorageStatus changed from Scoping to Under Construction/Commissioning
- Holmston Farm Battery Energy Storage SystemSouth Scotland, StorageConnection date moved from 30 Jun 2025 to 31 Jul 2026 (+13 months)+13 mo
- Holmston Farm Battery Energy Storage SystemSouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Ayr Energy StorageSouth Scotland, StorageSubstation name updated in the register (from Ayr 275/33kV to Ayr 275/33kV Substation)
- Ayr Energy StorageSouth Scotland, StorageConnection date moved from 30 Oct 2027 to 30 Oct 2028 (+12 months)+12 mo
- Ayr Energy StorageSouth Scotland, StorageStatus changed from Scoping to Consents Approved
- Ayr Energy StorageSouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Ayr Energy StorageSouth Scotland, StorageConnection date moved from 30 Apr 2027 to 30 Oct 2027 (+6 months)+6 mo
- Clonmacate Farm BESSSouth Scotland, StorageRenamed from Cloverhill Farm BESS
- Clonmacate Farm BESSSouth Scotland, StorageCustomer changed from Apatura Battery Ltd to GPC Project 11 Ltd
- Holmston Farm Battery Energy Storage SystemSouth Scotland, StorageCustomer changed from Field Devco Ltd to Field Holmston Ltd
- FPE Ayr BESSSouth Scotland, StorageAdded to the registerNew
- Holmston Farm Battery Energy Storage SystemSouth Scotland, StorageCustomer changed from Renewable Energy Systems Limited to Field Devco Ltd
- Ayr Energy StorageSouth Scotland, StorageSubstation name updated in the register (from Ayr 275/33 kV Substation to Ayr 275/33kV)
- Clonmacate Farm BESSSouth Scotland, StorageSubstation name updated in the register (from Ayr 275/33 kV Substation to Ayr 275/33kV)
- Holmston Farm Battery Energy Storage SystemSouth Scotland, StorageSubstation name updated in the register (from Ayr 275/33 kV Substation to Ayr 275/33kV)
- Ayr Energy StorageSouth Scotland, StorageCustomer changed from Cragside Energy Limited to KXP ALPHA I LIMITED
- Clonmacate Farm BESSSouth Scotland, StorageCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
- Clonmacate Farm BESSSouth Scotland, StorageAdded to the registerNew
- Ayr Energy StorageSouth Scotland, StorageAdded to the registerNew
- Holmston Farm Battery Energy Storage SystemSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?