FPE Ayr BESS
- Connection date
- 30 Oct 2037
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-004532
- In the register since
- June 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jun 2025 registerAdded to the register
Also at Ayr 275/33kV
Substation view3 other projects, 550 MW still to connect at this substation in total. 350 MW is due to connect here before this project’s connection date of 30 Oct 2037.