Holmston Farm Battery Energy Storage System
- Connection date
- Connected
- Gate
- Gate 2
- Status
- Built
- Planning consent
- Granted 30 Jun 2023
South Ayrshire, reference 22/00505/PAN · Source: REPD - Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 49.9 MW
- Still to connect
- 0 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-002359
- In the register since
- March 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Oct 2026 register49.9 MW now connected
- 30 Oct 2026 registerStatus changed from Under Construction/Commissioning to Built
- 18 Sep 2026 registerStatus changed from Scoping to Under Construction/Commissioning
- 30 Jun 2026 registerConnection date moved from 30 Jun 2025 to 31 Jul 2026 (+13 months)
- 30 Jun 2026 registerGiven a Gate 2 connection offer
- 29 Jul 2025 registerCustomer changed from Field Devco Ltd to Field Holmston Ltd
- 27 Jun 2025 registerCustomer changed from Renewable Energy Systems Limited to Field Devco Ltd
- 27 Sep 2024 registerSubstation name updated in the register (from Ayr 275/33 kV Substation to Ayr 275/33kV)
- 31 Mar 2023 registerAdded to the register
Also at Ayr 275/33kV
Substation view3 other projects, 550 MW still to connect at this substation in total.