Ayr Energy Storage
- Connection date
- 30 Oct 2028 +12 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 150 MW
- Connected now
- 0 MW
- Still to connect
- 150 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003801
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 23 Jun 2026 registerSubstation name updated in the register (from Ayr 275/33kV to Ayr 275/33kV Substation)
- 23 Jun 2026 registerConnection date moved from 30 Oct 2027 to 30 Oct 2028 (+12 months)
- 23 Jun 2026 registerStatus changed from Scoping to Consents Approved
- 23 Jun 2026 registerGiven a Gate 2 connection offer
- 30 Sep 2025 registerConnection date moved from 30 Apr 2027 to 30 Oct 2027 (+6 months)
- 27 Sep 2024 registerSubstation name updated in the register (from Ayr 275/33 kV Substation to Ayr 275/33kV)
- 28 Jun 2024 registerCustomer changed from Cragside Energy Limited to KXP ALPHA I LIMITED
- 30 Jun 2023 registerAdded to the register
Also at Ayr 275/33kV
Substation view3 other projects, 550 MW still to connect at this substation in total.