Bradenham - Thetford (Necton) GEC (Ethos Green)
- Connection date
- 1 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Demand + Storage + Solar + Reactive compensation
- Total capacity
- 850 MW
- Connected now
- 0 MW
- Still to connect
- 850 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004346
- In the register since
- October 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 26 Jun 2026 registerMarked as Gate 1
- 31 Oct 2023 registerAdded to the register
Also at Necton 400kV Substation
Substation view6 other projects, 5.2 GW still to connect at this substation in total. 4 GW is due to connect here before this project’s connection date of 1 Oct 2033.
- VanguardNORFOLK VANGUARD WEST LIMITED, Offshore wind, Gate 2Dec 20271.3 GW
- Vanguard EastNorfolk Vanguard East Ltd, Offshore wind, Gate 2Apr 20281.3 GW
- Norfolk BoreasNORFOLK BOREAS LIMITED, Offshore wind, Not statedOct 20291.3 GW
- Necton Greener Grid ParkNecton Grid Solutions Limited, Storage, Not statedOct 203278 MW
- Zenobe Necton BESSZENOBE ENERGY LIMITED, Storage, Gate 1Oct 2034300 MW
- Dudgeon Offshore Wind FarmDUDGEON OFFSHORE WIND LIMITED, Offshore wind, Not statedConnected400 MW