Eaton Socon High Impact Green Energy Hub (HIGEH) 1
- Connection date
- 30 Oct 2033
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Nuclear + Solar + Reactive compensation + Onshore wind
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002656
- In the register since
- July 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 12 Dec 2025 registerSubstation name updated in the register (from Eaton Socon GSP to Eaton Socon 400kV Substation)
- 27 Jun 2025 registerSubstation name updated in the register (from Eaton Socon 400kV Substation to Eaton Socon GSP)
- 27 Jun 2025 registerTechnology changed from Storage, Nuclear, Solar, Onshore wind to Storage, Nuclear, Solar, Reactive compensation, Onshore wind
- 27 Feb 2024 registerStatus changed from Awaiting Consents to Scoping
- 29 Aug 2023 registerSubstation name updated in the register (from Eaton Socon GSP to Eaton Socon 400kV Substation)
- 28 Jul 2023 registerAdded to the register
Also at Eaton Socon 400kV Substation
Substation view3 other projects, 1.5 GW still to connect at this substation in total. 550 MW is due to connect here before this project’s connection date of 30 Oct 2033.