- Connection date
- 30 Apr 2027 +20 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Storage
- Total capacity
- 50 MW
- Connected now
- 0 MW
- Still to connect
- 50 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001132
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 20 Oct 2026 registerConnection date moved from 5 Sep 2025 to 30 Apr 2027 (+20 months)
- 20 Oct 2026 registerStatus changed from Scoping to Under Construction/Commissioning
- 20 Oct 2026 registerGiven a Gate 2 connection offer
- 28 Mar 2025 registerCapacity changed from 49.5 MW to 50 MW
- 28 Mar 2025 registerConnection date moved from 1 May 2024 to 5 Sep 2025 (+16 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Sundon 400kV to Sundon 400kV Substation)
- 31 May 2022 registerCustomer changed from CSE21 LIMITED to SUNDON BATTERY STORAGE LIMITED
- 31 May 2022 registerConnection date moved from 10 May 2024 to 1 May 2024 (9 days earlier)
- 31 Dec 2021 registerTechnology changed from Gas (CCGT) to Storage
- 31 Aug 2021 registerConnection date moved from 13 Oct 2023 to 10 May 2024 (+7 months)
- 28 May 2021 registerConnection date moved from 1 Jul 2022 to 13 Oct 2023 (+15 months)
- 26 Feb 2021 registerConnection date moved from 7 Jan 2022 to 1 Jul 2022 (+6 months)
Also at Sundon 400kV Substation
Substation view3 other projects, 1.2 GW still to connect at this substation in total.