SUNDON BATTERY STORAGE LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Sundon | Sundon 400kV Substation | Storage | 50 | 30 Apr 2027 +20 mo | Gate 2 | Under Construction/Commissioning |
Recent changes
- SundonEngland and Wales, StorageConnection date moved from 5 Sep 2025 to 30 Apr 2027 (+20 months)+20 mo
- SundonEngland and Wales, StorageStatus changed from Scoping to Under Construction/Commissioning
- SundonEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- SundonEngland and Wales, StorageCapacity changed from 49.5 MW to 50 MW
- SundonEngland and Wales, StorageConnection date moved from 1 May 2024 to 5 Sep 2025 (+16 months)+16 mo
- SundonEngland and Wales, StorageSubstation name updated in the register (from Sundon 400kV to Sundon 400kV Substation)
- SundonEngland and Wales, StorageCustomer changed from CSE21 LIMITED to SUNDON BATTERY STORAGE LIMITED
- SundonEngland and Wales, StorageConnection date moved from 10 May 2024 to 1 May 2024 (9 days earlier)
- SundonEngland and Wales, StorageTechnology changed from Gas (CCGT) to Storage
- SundonEngland and Wales, StorageConnection date moved from 13 Oct 2023 to 10 May 2024 (+7 months)+7 mo
- SundonEngland and Wales, StorageConnection date moved from 1 Jul 2022 to 13 Oct 2023 (+15 months)+15 mo
- SundonEngland and Wales, StorageConnection date moved from 7 Jan 2022 to 1 Jul 2022 (+6 months)+6 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?