Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Llanwern Phase 2

FUTURE ENERGY LLANWERN LIMITED at Whitson 275kV Substation

Connection date
1 Oct 2028
Gate
Not stated
Status
Awaiting Consents
Technology
Solar
Total capacity
190 MW
Connected now
0 MW
Still to connect
190 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001125
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 13 Oct 2026 register
    Technology changed from Solar, Onshore wind to Solar
  • 29 Jul 2025 register
    Technology changed from Storage, Solar to Solar, Onshore wind
  • 29 Sep 2023 register
    Customer changed from GREENFIELDS (Q) LIMITED to FUTURE ENERGY LLANWERN LIMITED
  • 30 May 2023 register
    Connection point changed from Whitson 275/33kV Substation to Whitson 275kV Substation
  • 23 Dec 2022 register
    Connection point changed from Whitson 275kV to Whitson 275/33kV Substation
  • 29 Apr 2022 register
    Connection date moved from 30 Sep 2023 to 1 Oct 2028 (+60 months)

Also at Whitson 275kV Substation

Substation view

3 other projects, 485 MW still to connect at this substation in total. 49.9 MW is due to connect here before this project’s connection date of 1 Oct 2028.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO