Llanwern Phase 2
- Connection date
- 1 Oct 2028
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Solar
- Total capacity
- 190 MW
- Connected now
- 0 MW
- Still to connect
- 190 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001125
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 13 Oct 2026 registerTechnology changed from Solar, Onshore wind to Solar
- 29 Jul 2025 registerTechnology changed from Storage, Solar to Solar, Onshore wind
- 29 Sep 2023 registerCustomer changed from GREENFIELDS (Q) LIMITED to FUTURE ENERGY LLANWERN LIMITED
- 30 May 2023 registerConnection point changed from Whitson 275/33kV Substation to Whitson 275kV Substation
- 23 Dec 2022 registerConnection point changed from Whitson 275kV to Whitson 275/33kV Substation
- 29 Apr 2022 registerConnection date moved from 30 Sep 2023 to 1 Oct 2028 (+60 months)
Also at Whitson 275kV Substation
Substation view3 other projects, 485 MW still to connect at this substation in total. 49.9 MW is due to connect here before this project’s connection date of 1 Oct 2028.