Llanwern Phase 1
- Connection date
- 1 Oct 2028
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage + Solar
- Total capacity
- 95 MW
- Connected now
- 0 MW
- Still to connect
- 95 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001124
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerCustomer changed from GREENFIELDS (T) LIMITED to FUTURE ENERGY LLANWERN LIMITED
- 26 Mar 2024 registerConnection date moved from 31 Oct 2028 to 1 Oct 2028 (−1 month)
- 30 Jun 2023 registerConnection point changed from Whitston 275kV to Whitson 275kV Substation
- 30 Jun 2023 registerConnection date moved from 1 Nov 2023 to 31 Oct 2028 (+60 months)
- 30 Jun 2023 registerTechnology changed from Solar to Storage, Solar
- 30 Jul 2021 registerStatus changed from Consents Approved to Awaiting Consents
- 26 Feb 2021 registerConnection date moved from 11 Jan 2023 to 1 Nov 2023 (+10 months)
Also at Whitson 275kV Substation
Substation view3 other projects, 485 MW still to connect at this substation in total. 49.9 MW is due to connect here before this project’s connection date of 1 Oct 2028.