Mannington
- Connection date
- 28 Apr 2028 −28 months since 9 Dec
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 47.5 MW
- Connected now
- 0 MW
- Still to connect
- 47.5 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001092
- In the register since
- April 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 7 Aug 2026 registerConnection date moved from 30 Aug 2030 to 28 Apr 2028 (−28 months)
- 27 Jun 2025 registerCapacity changed from 57 MW to 47.5 MW
- 27 Jun 2025 registerConnection date moved from 20 May 2025 to 30 Aug 2030 (+63 months)
- 27 Jun 2025 registerTechnology changed from Solar to Storage, Solar
- 28 Jul 2023 registerSubstation name updated in the register (from Mannington GSP to Mannington 400kV Substation)
- 28 Oct 2022 registerSubstation name updated in the register (from Mannington to Mannington GSP)
- 29 Apr 2022 registerAdded to the register
Also at Mannington 400kV Substation
Substation view2 other projects, 143 MW still to connect at this substation in total. 95 MW is due to connect here before this project’s connection date of 28 Apr 2028.