Mannington Tertiary
MANNINGTON ENERGY CENTRE LIMITED at Mannington 400kV Substation
- Connection date
- 30 Oct 2025
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 47.5 MW
- Connected now
- 0 MW
- Still to connect
- 47.5 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000464
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 May 2025 registerStatus changed from Scoping to Consents Approved
- 23 Dec 2022 registerSubstation name updated in the register (from Mannington 400kV to Mannington 400kV Substation)
- 23 Dec 2022 registerCapacity changed from 49.9 MW to 47.5 MW
- 23 Dec 2022 registerConnection date moved from 2 Apr 2024 to 30 Oct 2025 (+19 months)
- 26 Feb 2021 registerConnection date moved from 4 Feb 2024 to 2 Apr 2024 (+2 months)
Also at Mannington 400kV Substation
Substation view2 other projects, 143 MW still to connect at this substation in total.