Exeter BESS
- Connection date
- 30 Aug 2027
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 680 MW
- Connected now
- 0 MW
- Still to connect
- 680 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001666
- In the register since
- July 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 290 | 290 | 30 Aug 2027 | Gate 2 | Consents Approved |
| 2 | 0 | 390 | 680 | 31 Oct 2037 | Not stated | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerStage 1: Status changed from Awaiting Consents to Consents Approved
- 5 Oct 2026 registerStage 1: Given a Gate 2 connection offer
- 30 May 2025 registerRestructured from 1 stage (290 MW from 31 Aug 2027) to 2 stages (290 MW from 30 Aug 2027, 390 MW from 31 Oct 2037)
- 29 Apr 2025 registerRenamed from Exeter Solar PV & BESS
- 31 Jan 2023 registerCustomer changed from STATERA ENERGY LIMITED to Exeter Storage Limited
- 23 Dec 2022 registerCustomer changed from Exeter Storage Limited to STATERA ENERGY LIMITED
- 30 Aug 2022 registerCustomer changed from STATERA ENERGY LIMITED to Exeter Storage Limited
- 29 Jul 2022 registerAdded to the register
Also at Exeter 400kV Substation
Substation view3 other projects, 1.2 GW still to connect at this substation in total. 57 MW is due to connect here before this project’s connection date of 30 Aug 2027.