Bramford (Tertiary)
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 57 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001016
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerTechnology changed from Storage to Storage, Solar
- 28 Feb 2025 register57 MW now connected
- 28 Feb 2025 registerCustomer changed from PIVOTED POWER LLP to DAMSONGREEN ENERGYFARM LIMITED
- 28 Feb 2025 registerStatus changed from Awaiting Consents to Built
- 28 Jun 2024 registerConnection date moved from 31 Mar 2024 to 1 Nov 2023 (−5 months)
- 26 Apr 2024 registerConnection date moved from 1 Nov 2023 to 31 Mar 2024 (+5 months)
- 29 Sep 2023 registerCapacity changed from 49.9 MW to 57 MW
- 30 Mar 2022 registerSubstation name updated in the register (from Bramford 400kV to Bramford 400kV Substation)
- 26 Feb 2021 registerConnection date moved from 11 Jan 2023 to 1 Nov 2023 (+10 months)
Also at Bramford 400kV Substation
Substation view6 other projects, 1.2 GW still to connect at this substation in total.
- Bramford TertiaryBRAMFORD GREEN LIMITED, Storage with solar or wind, Not statedJul 202657 MW
- Bramford BESSCSE33 LIMITED, Storage, Not statedNov 2029300 MW
- Alcemi Bramford Battery Energy Storage FacilityALCEMI STORAGE DEVELOPMENTS 1 LIMITED, Storage, Gate 1Oct 2030500 MW
- Bramford 2 GEC (Ethos Green)BRAMFORD 2 GREEN ENERGY CENTRE LTD, Storage with solar or wind, Not statedJul 203257 MW
- ER BRF 2 EnergyER PROJECT DEVELOPMENT CO LIMITED, Storage with solar or wind, Gate 1Jul 2033249 MW
- ThetfordEPR THETFORD LIMITED, Thermal (gas, biomass, waste), Not statedConnected41 MW