QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Buttington Quarry

Broad Energy Wales Ltd at Legacy

SPEN Embedded Capacity Register >1MW, June 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
Not stated
Status
Accepted to connect
Customer
Broad Energy Wales Ltd
Site name
Buttington Quarry
Address
Criggion Lane Trewern To Buttington Cross, Buttington, Welshpool, Dee Valley and Mid Wales, SY21 8ST
Grid reference
Easting 326440, northing 309818
Licence area
Merseyside, Cheshire and North Wales (SPM)
Grid supply point
Legacy
Bulk supply point
LEGACY LOCAL GT2 / NEWTOWN GT2 / OSWESTRY GT5 / OSWESTRY GT8 / WELSHPOOL GT1 / WHITCHURCH GT1
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Gas and other fossil
Energy source 1
Fossil - Gas, Steam-gas turbine (CCGT): 12.5 MW registered
Registered capacity
12.5 MW
Change to maximum export capacity
12.5 MW
Change to maximum import capacity
0 MW
Flexible connection
Not stated
In a connection queue
Yes
Date accepted
Not stated
Date connected
Not stated
Distribution reinforcement reference
Not published by SPEN
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
14 Sep 2020
Tracked since
March 2026 edition

Change history

Tracked from the March 2026 edition to the June 2026 edition, across 4 editions.

Changes to the details QueueWatch tracks, newest first.

  • July 2026 edition
    Not found among this edition’s sites of 1 MW and over by its MPAN, grid reference or name and postcode

No change to any detail QueueWatch tracks.

Also at Legacy

GSP view

49 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 615 MW: 328 MW connected, 287 MW accepted to connect.

See all 49

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?