QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Distribution / SPEN / Grid supply point

Killermont

Grid supply point in Central and Southern Scotland (SPD)

SPEN Embedded Capacity Register >1MW, September 2026 edition

6sites of 1 MW and over
82.6 MWcapacity
11.2 MWconnected (3 sites)
71.4 MWaccepted to connect (3 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage150.4 MW–50.4 MW
Solar326.2 MW5.1 MW21.1 MW
Bioenergy and waste15 MW5 MW–
Gas and other fossil11 MW1 MW–

Storage capacity in MWh: not published by SPEN.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
Not stated2–68.8 MW
Not stated25.1 MW2.7 MW
Not stated15 MW–
Not stated11 MW–

Search and filter all 6 sites at Killermont

What changed recently

Changes to sites here found in both editions of each pair, newest first.

August 2026 edition to September 2026 edition: 6 sites matched. Every August site and every September site at this grid supply point had a match in the other edition.

  • Lochfauld Solar ParkSeptember 2026 editionTarget energisation date moved from 30 Aug 2026 to 9 Oct 2026 (1 month later)
  • Lochfauld Solar ParkAugust 2026 editionTarget energisation date moved from 30 Jul 2026 to 30 Aug 2026 (1 month later)
  • Balmore WTWMay 2026 editionCustomer changed from SP Distribution plc to FES Support Services
  • Balmore WTW ExtensionMay 2026 editionCustomer stated as Scottish Water Horizons Limited (not stated in the April 2026 edition)
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.