QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

WESTERFIELD FARM

WESTERFIELD SOLAR LIMITED at COWLEY GSP

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
23 Mar 2015
Status
Connected
Planning consent
Granted on appeal 1 Dec 2014
West Oxfordshire, reference 13/1534/P/FP · Source: REPD
Customer
WESTERFIELD SOLAR LIMITED
Site name
WESTERFIELD FARM
Address
WESTERFIELD FARM PV, OXFORD, OXFORDSHIRE, OX18 3NX
Grid reference
Easting 428766, northing 208858
Licence area
Southern England (SEPD)
Grid supply point
COWLEY GSP
Bulk supply point
WITNEY
Primary substation
WESTERFIELD FM SHIL PV
Connection voltage
33 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 9.405 MW registered
Registered capacity
9.405 MW
Maximum export capacity
9.405 MW
Maximum import capacity
Not stated
Flexible connection
No
In a connection queue
Not published by SSEN
Date accepted
Not stated
Target energisation date
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
2000056222894
Import MPAN
2000056222885
Last updated
12 Feb 2026
Tracked since
August 2023 edition

Change history

Tracked since the August 2023 edition, across 40 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at COWLEY GSP

GSP view

71 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 2.0 GW: 0.4 GW connected, 1.6 GW accepted to connect.

See all 71

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.