WESTER COVESEA SOLAR, WIND AND STORAGE

BSR APPLICATIONS LIMITED at ELGIN

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
30 Jun 2032
Status
Accepted to connect
Customer
BSR APPLICATIONS LIMITED
Site name
WESTER COVESEA SOLAR, WIND AND STORAGE
Address
WESTER COVESEA SOLAR, WIND AND STORAGE, LAND AT EASTEND AND WESTEND DUFFUS, ELGIN, MORAY, IV30 5QS
Grid reference
Easting 317812, northing 869728
Licence area
North of Scotland (SHEPD)
Grid supply point
ELGIN
Bulk supply point
Not stated
Primary substation
ELGIN GRID
Connection voltage
33 kV
Technology group
Wind
Energy source 1
WIND, ONSHORE WIND TURBINES: 180 MW registered
Energy source 2
STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 60 MW registered
Registered capacity
180 MW
Change to maximum export capacity
60 MW
Change to maximum import capacity
63.208 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
16 Dec 2024
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
January 2025 edition

Change history

Tracked since the January 2025 edition, across 23 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 30 Jun 2032 (not stated in the October 2025 edition)

Also at ELGIN

GSP view

7 other sites at this grid supply point in the November 2026 edition, 6 of them at ELGIN GRID, the same primary substation. In all, the sites here total 525 MW: 525 MW accepted to connect.

  • ELGIN BESS FARMGF ELGIN ENERGY, Storage, ELGIN GRID primaryAccepted105.36 MW
  • MILLTOWN PVDNO CONSULTING, Solar, ELGIN GRID primaryAccepted99.8 MW
  • LOANHEAD FARMOPD ENERGY UK LTD, Storage, ELGIN GRID primaryAccepted52.68 MW
  • WESTFIELD SOLAR & STORAGEEUROPEAN ENERGY UK LIMITED, Solar, ELGIN GRID primaryAccepted50 MW
  • ELGIN BESS STORAGEGREEN POWER CONSULTANTS LIMITED, Storage, ELGIN GRID primaryAccepted30 MW
  • RAF LOSSIEMOUTHDEFENCE INFASTRUCTURE ORGANISATION, Solar, ELGIN GRID primaryAccepted4.95 MW
  • KINLOSS BARRACKS PVDEFENCE INFRASTRUCTURE ORGANISATION, Solar, KINLOSS primaryAccepted2.64 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?