ELGIN
Grid supply point in North of Scotland (SHEPD)
SSEN Embedded Capacity Register, November 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Storage | 3 | 188 MW | – | 188 MW |
| Wind | 1 | 180 MW | – | 180 MW |
| Solar | 4 | 157 MW | – | 157 MW |
Storage capacity in MWh: not published by SSEN.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | ||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Not stated | 7 | – | 523 MW | |||||||||||||||||||||||||||||||||||||||||
7 sites, 523 MW: 523 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 1 | – | 2.6 MW | |||||||||||||||||||||||||||||||||||||||||
1 site, 2.6 MW: 2.6 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||
Listed at under 1 MW in SSEN’s November 2026 edition
1 site last listed here at 1 MW or over is listed in this edition at under 1 MW. QueueWatch keeps its page for six months.
- DGEN ELGIN last found in the October 2026 edition
What changed recently
Changes to sites here found in both editions of each pair, newest first.
October 2026 edition to November 2026 edition: 8 sites matched. 1 site at this grid supply point couldn’t be matched between the two editions, because its details changed or it appears in only one.
1 site without a match in the other edition
In the October 2026 edition only (1)
- DGEN ELGINNorth of Scotland (SHEPD)Accepted to connectListed at under 1 MW in the November 2026 edition0.07 MW
- WESTFIELD SOLAR & STORAGENovember 2026 editionExport capacity changed from 52.631 MW to 50 MW
- WESTFIELD SOLAR & STORAGEOctober 2026 editionExport capacity changed from 50 MW to 52.631 MW
- KINLOSS BARRACKS PVSeptember 2026 editionExport capacity changed from 2.64 MW to 0 MW
- WESTFIELD SOLAR & STORAGESeptember 2026 editionExport capacity changed from 52.631 MW to 50 MW
- WESTFIELD SOLAR & STORAGEAugust 2026 editionExport capacity changed from 50 MW to 52.631 MW
- KINLOSS BARRACKS PVJuly 2026 editionExport capacity changed from 0 MW to 2.64 MW
- WESTFIELD SOLAR & STORAGEMay 2026 editionExport capacity changed from 52.631 MW to 50 MW
- WESTFIELD SOLAR & STORAGEApril 2026 editionExport capacity changed from 50 MW to 52.631 MW
- KINLOSS BARRACKS PVFebruary 2026 editionExport capacity changed from 2.08 MW to 0 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.