MACDUFF
Grid supply point in North of Scotland (SHEPD)
SSEN Embedded Capacity Register, November 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Solar | 4 | 164 MW | – | 164 MW |
| Other or not stated | 2 | 70 MW | 21.8 MW | 48.2 MW |
| Wind | 13 | 61.3 MW | 56.7 MW | 4.6 MW |
| Storage | 1 | 52.7 MW | – | 52.7 MW |
| Bioenergy and waste | 1 | 49.9 MW | – | 49.9 MW |
Storage capacity in MWh: not published by SSEN.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Not stated | 17 | 71 MW | 319 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
17 sites, 390 MW: 71 MW connected, 319 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 2 | 4.1 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 4.1 MW: 4.1 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 1 | 2.3 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 2.3 MW: 2.3 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 1 | 1.7 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1.7 MW: 1.7 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
What changed recently
Changes to sites here found in both editions of each pair, newest first.
October 2026 edition to November 2026 edition: 21 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.
- DENHEAD SOLAR MACDUFF GSPNovember 2026 editionExport capacity changed from 20 MW to 0.1 MW
- MOUNT BLAIRY SOLAR FARM BROWNSIDE FARMNovember 2026 editionExport capacity changed from 35.2 MW to 0.8 MW
- MOUNT BLAIRY SOLAR FARM BROWNSIDE FARMOctober 2026 editionExport capacity changed from 0.8 MW to 35.2 MW
- DENHEAD SOLAR MACDUFF GSPSeptember 2026 editionExport capacity changed from 0.1 MW to 20 MW
- MOUNT BLAIRY SOLAR FARM BROWNSIDE FARMAugust 2026 editionExport capacity changed from 35.2 MW to 0.8 MW
- DENHEAD SOLAR MACDUFF GSPJuly 2026 editionExport capacity changed from 20 MW to 0.1 MW
- DENHEAD SOLAR MACDUFF GSPMay 2026 editionExport capacity changed from 0.1 MW to 20 MW
- DENHEAD SOLAR MACDUFF GSPApril 2026 editionExport capacity changed from 20 MW to 0.1 MW
- DENHEAD SOLAR MACDUFF GSPJune 2025 editionFlexible connection not stated (“no” in the May 2025 edition)
- DENHEAD SOLAR MACDUFF GSPJune 2025 editionTechnology changed from Bioenergy and waste to Solar
- BOYNDIE WINDFARMApril 2025 editionTechnology stated as Wind (not stated in the March 2025 edition)
- BENZIESFebruary 2025 editionTechnology stated as Wind (not stated in the January 2025 edition)
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.