BETTYHILL PHASE 2 WINDFARM

EDEN RENEWABLES at DOUNREAY

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
1 Nov 2027
Status
Accepted to connect
Customer
EDEN RENEWABLES
Site name
BETTYHILL PHASE 2 WINDFARM
Address
BETTYHILL PHASE 2 WINDFARM, SKELPICK ESTATE, BETTYHILL, HIGHLAND, KW14 7TB
Grid reference
Easting 274555, northing 963588
Licence area
North of Scotland (SHEPD)
Grid supply point
DOUNREAY
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Wind
Energy source 1
WIND, ONSHORE WIND TURBINES: 96 MW registered
Energy source 2
STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 50.526 MW registered
Registered capacity
96 MW
Change to maximum export capacity
48 MW
Change to maximum import capacity
50.526 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
26 Oct 2021
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
August 2023 edition

Change history

Tracked since the August 2023 edition, across 40 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 1 Nov 2027 (not stated in the October 2025 edition)

Also at DOUNREAY

GSP view

8 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 381 MW: 63 MW connected, 318 MW accepted to connect.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose