QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

HIGGLERS FARM

Name not shown at BOTLEY WOOD GSP

SSEN Embedded Capacity Register, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
6 Dec 2036
Status
Accepted to connect
Customer
Name not shown
Site name
HIGGLERS FARM
Address
HIGGLERS FARM, TITCHFIELD LANE, FAREHAM, HAMPSHIRE, PO17 5PQ
Grid reference
Easting 455620, northing 110613
Licence area
Southern England (SEPD)
Grid supply point
BOTLEY WOOD GSP
Bulk supply point
BOTLEY WOOD
Primary substation
BOTLEY WOOD
Connection voltage
33 kV
Technology group
Storage
Energy source 1
STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 49.99 MW registered
Registered capacity
49.99 MW
Change to maximum export capacity
49.99 MW
Change to maximum import capacity
55.291 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
2 Dec 2022
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
December 2025 edition

Change history

Tracked since the December 2025 edition, across 10 editions.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at BOTLEY WOOD GSP

GSP view

16 other sites at this grid supply point in the September 2026 edition, 2 of them at BOTLEY WOOD, the same primary substation. In all, the sites here total 421 MW: 103 MW connected, 318 MW accepted to connect.

See all 16

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose