QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

FLOTTA TERMINAL

TALISMAN ENERGY UK LTD at THURSO

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
Not stated
Status
Connected
Customer
TALISMAN ENERGY UK LTD
Site name
FLOTTA TERMINAL
Address
FLOTTA TERMINAL EXPORT, STROMNESS, ORKNEY ISLANDS, KW16 3NP
Grid reference
Easting 336349, northing 993692
Licence area
North of Scotland (SHEPD)
Grid supply point
THURSO
Bulk supply point
Not stated
Primary substation
SCORRADALE
Connection voltage
33 kV
Technology group
Wind
Energy source 1
WIND, ONSHORE WIND TURBINES: 9.5 MW registered
Registered capacity
9.5 MW
Maximum export capacity
9.5 MW
Maximum import capacity
Not stated
Flexible connection
No
In a connection queue
Not published by SSEN
Date accepted
Not stated
Target energisation date
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
1700051732151
Import MPAN
1700051622272
Last updated
12 Feb 2026
Tracked since
August 2023 edition

Change history

Tracked since the August 2023 edition, across 40 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at THURSO

GSP view

24 other sites at this grid supply point in the November 2026 edition, 8 of them at SCORRADALE, the same primary substation. In all, the sites here total 379 MW: 38 MW connected, 341 MW accepted to connect.

See all 24

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?