THURSO
Grid supply point in North of Scotland (SHEPD)
SSEN Embedded Capacity Register, November 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Wind | 19 | 283 MW | 34 MW | 249 MW |
| Hydro and marine | 6 | 95.9 MW | 3.8 MW | 92.1 MW |
Storage capacity in MWh: not published by SSEN.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the November 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | ||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Not stated | 2 | – | 55.2 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 55.2 MW: 55.2 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 9 | 27.1 MW | 12.9 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||
9 sites, 40 MW: 27.1 MW connected, 12.9 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 1 | 3.8 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 3.8 MW: 3.8 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 2 | 2.9 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 2.9 MW: 2.9 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 1 | 2.1 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 2.1 MW: 2.1 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 1 | 1.7 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1.7 MW: 1.7 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 9 | – | 273 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||
9 sites, 273 MW: 273 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
Not found among the sites of 1 MW and over in SSEN’s November 2026 edition
2 sites last found at this grid supply point were not found among this edition’s sites of 1 MW and over by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.
- ORKNEY COMMUNITY WIND FARM PROJECT last found in the June 2026 edition
- RENNIBISTER II WIND last found in the May 2026 edition
What changed recently
Changes to sites here found in both editions of each pair, newest first.
October 2026 edition to November 2026 edition: 25 sites matched. Every October site and every November site at this grid supply point had a match in the other edition.
- EDAY TIDAL DEVELOPMENTSNovember 2026 editionExport capacity changed from 4.8 MW to 0.1 MW
- EDAY TIDAL DEVELOPMENTSOctober 2026 editionExport capacity changed from 0.1 MW to 4.8 MW
- EDAY TIDAL DEVELOPMENTSSeptember 2026 editionExport capacity changed from 4.8 MW to 0.1 MW
- CRACKA LONGI WINDAugust 2026 editionExport capacity changed from 8.421 MW to 8.4 MW
- 4.8MW TIDALJuly 2026 editionFlexible connection stated as “yes” (not stated in the June 2026 edition)
- WORK FARM, WORK FARMJuly 2026 editionFlexible connection stated as “yes” (not stated in the June 2026 edition)
- EDAY TIDAL DEVELOPMENTSJune 2026 editionExport capacity changed from 0.1 MW to 4.8 MW
- CRACKA LONGI WINDMay 2026 editionExport capacity changed from 8.4 MW to 8.421 MW
- EDAY TIDAL DEVELOPMENTSMay 2026 editionExport capacity changed from 4.8 MW to 0.1 MW
- EDAY TIDAL DEVELOPMENTSApril 2026 editionExport capacity changed from 0.1 MW to 4.8 MW
- EDAY TIDAL DEVELOPMENTSFebruary 2026 editionExport capacity changed from 4.8 MW to 0.1 MW
- BURGAR HILLApril 2025 editionTechnology stated as Wind (not stated in the March 2025 edition)
- BURGAR HILLNovember 2023 editionTechnology not stated (Wind in the October 2023 edition)
- THORFINN A WIND ENERGY PROJECTNovember 2023 editionCustomer changed from ORKNEY WIND TURBINE NM1500 to ORKNEY WIND TURBINE NM15DATA NOT AVAILABLEDATA NOT AVAILABLE
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.