MEREOAK PARK AND RIDE

At BRAMLEY (FLEE)

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
23 Apr 2026
Status
Accepted to connect
Planning consent
Granted 10 Nov 2025
Wokingham, reference 252226 · Source: REPD
Customer
Not stated
Site name
MEREOAK PARK AND RIDE
Address
MEREOAK PARK AND RIDE, READING, WOKINGHAM, RG7 1JY
Grid reference
Easting 469946, northing 166791
Licence area
Southern England (SEPD)
Grid supply point
BRAMLEY (FLEE)
Bulk supply point
BURGHFIELD MAIN
Primary substation
WHITLEY WOOD
Connection voltage
11 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 1 MW registered
Registered capacity
1 MW
Change to maximum export capacity
1 MW
Change to maximum import capacity
0.053 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
18 Dec 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
January 2024 edition

Change history

Tracked since the January 2024 edition, across 35 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 23 Apr 2026 (not stated in the October 2025 edition)

Also at BRAMLEY (FLEE)

GSP view

67 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 1.6 GW: 0.4 GW connected, 1.2 GW accepted to connect.

See all 67

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.