MILLENNIUM EAST WIND FARM

MILLENNIUM EAST WIND FARM at FORT AUGUSTUS

SSEN Embedded Capacity Register, October 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2035
Status
Accepted to connect
Planning consent
Application submitted 13 Aug 2025
Scottish Government (S36), reference ECU00005013 · Source: REPD
Customer
MILLENNIUM EAST WIND FARM
Site name
MILLENNIUM EAST WIND FARM
Address
MILLENNIUM EAST WIND FARM, GLENMORISTON, INVERNESS, HIGHLAND, IV63 7YN
Grid reference
Easting 227912, northing 812485
Licence area
North of Scotland (SHEPD)
Grid supply point
FORT AUGUSTUS
Bulk supply point
Not stated
Primary substation
FORT AUGUSTUS GRID
Connection voltage
33 kV
Technology group
Wind
Energy source 1
WIND, ONSHORE WIND TURBINES: 49.9 MW registered
Registered capacity
49.9 MW
Change to maximum export capacity
49.9 MW
Change to maximum import capacity
2.769 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
15 Mar 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
August 2023 edition

Change history

Tracked since the August 2023 edition, across 39 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 31 Oct 2035 (not stated in the October 2025 edition)

Also at FORT AUGUSTUS

GSP view

4 other sites at this grid supply point in the October 2026 edition, 3 of them at FORT AUGUSTUS GRID, the same primary substation. In all, the sites here total 172 MW: 51 MW connected, 121 MW accepted to connect.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.