Winterton PV
Winterton PV at Keadby
Northern Powergrid Embedded Capacity Register 1MW and Over, July 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- Not published by Northern Powergrid
- Status
- Accepted to connect
- Customer
- Winterton PV
- Site name
- Winterton PV
- Address
- CARR LANE, Winterton, SOUTH FERRIBY, Lincolnshire, DN15 8RF
- Grid reference
- Easting 489827, northing 412823
- Licence area
- Yorkshire (Northern Powergrid)
- Grid supply point
- Keadby
- Bulk supply point
- Santon
- Primary substation
- South Ferriby
- Connection voltage
- 11 kV
- Technology group
- Solar
- Energy source 1
- Solar, Photovoltaic: 6.96 MW registered
- Registered capacity
- 6.96 MW
- Change to maximum export capacity
- 6.96 MW
- Change to maximum import capacity
- Not stated
- Flexible connection
- No
- In a connection queue
- Not published by Northern Powergrid
- Date accepted
- 29 Apr 2021
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by Northern Powergrid
- Transmission reinforcement reference
- Not published by Northern Powergrid
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 8 May 2024
- Tracked since
- March 2026 edition
Change history
Tracked from the March 2026 edition to the July 2026 edition, across 5 editions.
Changes to the details QueueWatch tracks, newest first.
- August 2026 editionNot found among this edition’s sites of 1 MW and over by its MPAN, grid reference or name and postcode
No change to any detail QueueWatch tracks.
Also at Keadby
GSP view69 other sites at this grid supply point in the November 2026 edition, 3 of them at South Ferriby, the same primary substation. In all, the sites here total 2.5 GW: 0.6 GW connected, 1.9 GW accepted to connect.
- Elm Tree Solar Wind & BESSElm Tree Solar Wind & BESS, Storage, Elm Tree Hybrid Direct primaryAccepted394.6 MW
- Ludborough Solar FarmLudborough Solar Farm, Solar, Ludborough Solar Farm Direct primaryAccepted98 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose