Ray Wind Farm Additional BESS
Ray Wind Farm Additional BESS at Fourstones 33kV
Northern Powergrid Embedded Capacity Register 1MW and Over, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Date connected
- 28 Apr 2023
- Status
- Connected
- Customer
- Ray Wind Farm Additional BESS
- Site name
- Ray Wind Farm Additional BESS
- Address
- Ray Wind Farm, Kirkwhelpington, Hexham, Northumberland, NE19 2RJ
- Grid reference
- Easting 395603, northing 588982
- Licence area
- North East (Northern Powergrid)
- Grid supply point
- Fourstones 33kV
- Bulk supply point
- Fourstones 33kV
- Primary substation
- Ray Fell Windfarm
- Connection voltage
- 33 kV
- Technology group
- Storage
- Energy source 1
- Stored Energy (all stored energy irrespective of the original energy source), Storage - Electrochemical (Batteries): 20 MW registered
- Registered capacity
- 20 MW
- Maximum export capacity
- 20 MW
- Maximum import capacity
- Not stated
- Flexible connection
- No
- In a connection queue
- Not published by Northern Powergrid
- Date accepted
- 22 Oct 2020
- Target energisation date
- Not published by Northern Powergrid
- Distribution reinforcement reference
- Not published by Northern Powergrid
- Transmission reinforcement reference
- Not published by Northern Powergrid
- Export MPAN
- 1574300360030
- Import MPAN
- 1570000360027
- Last updated
- 18 Sep 2024
- Tracked since
- March 2026 edition
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Change history
Tracked since the March 2026 edition, across 9 editions.
Changes to the details QueueWatch tracks, newest first.
No change to any detail QueueWatch tracks.
Also at Fourstones 33kV
GSP view3 other sites at this grid supply point in the November 2026 edition, 1 of them at Ray Fell Windfarm, the same primary substation. In all, the sites here total 266 MW: 74 MW connected, 192 MW accepted to connect.
- Ray Windfarm, Kirkwhelpington (Ray Fell Windfarm)Ray Windfarm, Kirkwhelpington (Ray Fell Windfarm), Wind, Ray Fell Windfarm primaryConnected54.4 MW
- Fourstones Hybrid (Solar & BESS)Fourstones Hybrid (Solar & BESS), Storage, Fourstones Hybrid primaryAccepted80 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?