QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Next Distribution Centre Ltd

Next Distribution Centre Ltd at West Melton / Thorpe Marsh

Northern Powergrid Embedded Capacity Register 1MW and Over, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
13 Jul 2015
Status
Connected
Planning consent
Operational since 1 Dec 2016
Doncaster · Source: REPD
Customer
Next Distribution Centre Ltd
Site name
Next Distribution Centre Ltd
Address
Lincolnshire Way, Armthorpe, Doncaster, South Yorkshire, DN3 3FF
Grid reference
Easting 464019, northing 405100
Licence area
Yorkshire (Northern Powergrid)
Grid supply point
West Melton / Thorpe Marsh
Bulk supply point
Doncaster B/Thorpe Marsh
Primary substation
West Moor Park
Connection voltage
11 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 1.9 MW registered
Registered capacity
1.9 MW
Maximum export capacity
1.9 MW
Maximum import capacity
Not stated
Flexible connection
No
In a connection queue
Not published by Northern Powergrid
Date accepted
Not stated
Target energisation date
Not published by Northern Powergrid
Distribution reinforcement reference
Not published by Northern Powergrid
Transmission reinforcement reference
Not published by Northern Powergrid
Export MPAN
2394000123995
Import MPAN
Not stated
Last updated
8 Mar 2017
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 9 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at West Melton / Thorpe Marsh

GSP view

48 other sites at this grid supply point in the November 2026 edition, 2 of them at West Moor Park, the same primary substation. In all, the sites here total 1.2 GW: 0.3 GW connected, 0.9 GW accepted to connect.

See all 48

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.