Netherlands Way Gas
Netherlands Way Gas at Grimsby West
Northern Powergrid Embedded Capacity Register 1MW and Over, July 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- Not published by Northern Powergrid
- Status
- Accepted to connect
- Customer
- Netherlands Way Gas
- Site name
- Netherlands Way Gas
- Address
- OLD RAIL YARD, NETHERLANDS WAY, STALLINGBOROUGH, West Yorkshire, LS9 0PS
- Grid reference
- Easting 433626, northing 432153
- Licence area
- Yorkshire (Northern Powergrid)
- Grid supply point
- Grimsby West
- Bulk supply point
- Netherlands Way
- Primary substation
- Netherlands Way Gas
- Connection voltage
- 33 kV
- Technology group
- Gas and other fossil
- Energy source 1
- Fossil - Gas, Engine (combustion / reciprocating): 60 MW registered
- Registered capacity
- 60 MW
- Change to maximum export capacity
- 60 MW
- Change to maximum import capacity
- 14.25 MW
- Flexible connection
- Yes
- In a connection queue
- Not published by Northern Powergrid
- Date accepted
- 2 Mar 2021
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by Northern Powergrid
- Transmission reinforcement reference
- Not published by Northern Powergrid
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 15 Aug 2024
- Tracked since
- March 2026 edition
Change history
Tracked from the March 2026 edition to the July 2026 edition, across 5 editions.
Changes to its status, capacity, technology or customer, newest first.
- August 2026 editionNot found in this edition by its MPAN, grid reference or name and postcode
No change to its status, capacity, technology or customer.
Also at Grimsby West
GSP view46 other sites at this grid supply point in the September 2026 edition, 1 of them at Netherlands Way Gas, the same primary substation. In all, the sites here total 1.8 GW: 0.5 GW connected, 1.3 GW accepted to connect.
- Netherlands Way GasNetherlands Way Gas, Gas and other fossil, Netherlands Way Gas primaryAccepted60 MW
- Little Becks Solar, Wind and StorageLittle Becks Solar, Wind and Storage, Solar, Little Becks Hybrid Direct primaryAccepted299.7 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose