QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Europa Way

NEL Immingham BESS at Grimsby West

Northern Powergrid Embedded Capacity Register 1MW and Over, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
Not published by Northern Powergrid
Status
Accepted to connect
Planning consent
Granted 20 May 2025
North East Lincolnshire, reference DM/0484/24/FUL · Source: REPD
Customer
NEL Immingham BESS
Site name
Europa Way
Address
Europa Way Stallingborough, Grimsby, Immingham, Lincolnshire, DN41 8DT
Grid reference
Easting 520732, northing 414280
Licence area
Yorkshire (Northern Powergrid)
Grid supply point
Grimsby West
Bulk supply point
Netherlands Way
Primary substation
Immingham BESS Direct
Connection voltage
33 kV
Technology group
Storage
Energy source 1
Stored Energy (all stored energy irrespective of the original energy source), Storage - Electrochemical (Batteries): 80 MW registered
Registered capacity
80 MW
Change to maximum export capacity
80 MW
Change to maximum import capacity
80 MW
Flexible connection
Yes
In a connection queue
Not published by Northern Powergrid
Date accepted
15 Jun 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by Northern Powergrid
Transmission reinforcement reference
Not published by Northern Powergrid
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
23 Aug 2024
Tracked since
March 2026 edition

What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?

Change history

Tracked since the March 2026 edition, across 9 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Grimsby West

GSP view

46 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 1.8 GW: 0.5 GW connected, 1.3 GW accepted to connect.

See all 46

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.