RIGBY PV+BESS

INFINIS ENERGY SERVICES LIMITED at PENWORTHAM WEST GSP / STANAH GSP GROUP

ENWL Embedded Capacity Register 2 – 1MW and above, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
Not stated
Status
Accepted to connect
Customer
INFINIS ENERGY SERVICES LIMITED
Site name
RIGBY PV+BESS
Address
RIGBY LANDFILL SITE, CHORLEY ROAD, STANDISH, WIGAN, WN1 2XJ
Grid reference
Easting 358481, northing 412076
Licence area
North West England (ENWL)
Grid supply point
PENWORTHAM WEST GSP / STANAH GSP GROUP
Bulk supply point
WRIGHTINGTON
Primary substation
STANDISH
Connection voltage
11 kV
Technology group
Storage
Energy source 1
BATTERY & SOLAR, STORAGE - ELECTROCHEMICAL (BATTERIES): 4.26 MW registered
Registered capacity
4.26 MW
Maximum export capacity
0 MW
Maximum import capacity
0 MW
Change to maximum export capacity
4.26 MW
Change to maximum import capacity
4.26 MW
Flexible connection
No
In a connection queue
No
Date accepted
6 Jun 2022
Date connected
Not stated
Distribution reinforcement reference
Not published by ENWL
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
29 Jul 2022
Tracked since
May 2026 edition

Change history

Tracked since the May 2026 edition, across 2 editions.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at PENWORTHAM WEST GSP / STANAH GSP GROUP

GSP view

62 other sites at this grid supply point in the September 2026 edition, 3 of them at STANDISH, the same primary substation. In all, the sites here total 829 MW: 463 MW connected, 366 MW accepted to connect.

See all 62

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose