HILLSIDE FARM

HM HILLSIDE LTD at HEYSHAM GSP

ENWL Embedded Capacity Register 2 – 1MW and above, October 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
Not stated
Status
Accepted to connect
Planning consent
Granted 19 Sep 2023
Lancaster, reference 22/01317/FUL · Source: REPD
Customer
HM HILLSIDE LTD
Site name
HILLSIDE FARM
Address
HILLSIDE FARM, HEATON WITH OXCLIFFE, MORECAMBE, LANCASHIRE, LA3 3ET
Grid reference
Easting 343764, northing 460686
Licence area
North West England (ENWL)
Grid supply point
HEYSHAM GSP
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
132 kV
Technology group
Storage
Energy source 1
STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 50 MW registered
Registered capacity
50 MW
Maximum export capacity
0 MW
Maximum import capacity
0 MW
Change to maximum export capacity
50 MW
Change to maximum import capacity
50 MW
Flexible connection
No
In a connection queue
No
Date accepted
8 Apr 2022
Date connected
Not stated
Distribution reinforcement reference
Not published by ENWL
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
13 Jun 2022
Tracked since
May 2026 edition

What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?

Change history

Tracked since the May 2026 edition, across 3 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at HEYSHAM GSP

GSP view

29 other sites at this grid supply point in the October 2026 edition. In all, the sites here total 1.2 GW: 0.3 GW connected, 0.9 GW accepted to connect.

See all 29

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.