Vital Energi Solutions Limited

Customer named in the DNOs’ registers

In SSEN’s November 2026, SPEN’s September 2026 and ENWL’s October 2026 editions

The registers spell this customer’s name more than one way: “Vital Energi Solutions Limited” (4 sites) and “VITAL ENERGI SOLUTIONS LIMITED” (3 sites).

7sites of 1 MW and over
255 MWcapacity
4 MWconnected (2 sites)
251 MWaccepted to connect (5 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
SSENNovember 2026 edition299.8 MW–99.8 MW
SPENSeptember 2026 edition4154 MW3 MW151 MW
ENWLOctober 2026 edition11 MW1 MW–

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage5251 MW–251 MW
Gas and other fossil24 MW4 MW–

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs’ latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
Cleveden Road BESSSPENKillermontStorageAccepted to connect50.4
Helen Street BESSSPENGovanStorageAccepted to connect50.4
Provan Gas Works BESSSPENCarntyneStorageAccepted to connect50.4
CARSVIEW ROADSSENLUNANHEADStorageAccepted to connect49.9
MIDMILL GASHOLDER STATIONSSENMILTON OF CRAIGIEStorageAccepted to connect49.9
University of Edinburgh CHPSPENWhitehouseGas and other fossilConnected3
CHRISTIES HOSPICEENWLBREDBURY GSPGas and other fossilConnected1.04

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
CarntyneSPEN1–50.4 MW
GovanSPEN1–50.4 MW
KillermontSPEN1–50.4 MW
LUNANHEADSSEN1–49.9 MW
MILTON OF CRAIGIESSEN1–49.9 MW
WhitehouseSPEN13 MW–
BREDBURY GSPENWL11 MW–

What changed recently

Changes to its sites found in both editions of each pair, newest first.

SSEN, October 2026 edition to November 2026 edition, for this customer’s sites: 2 sites matched. Every October site and every November site had a match in the other edition.

SPEN, August 2026 edition to September 2026 edition, for this customer’s sites: 4 sites matched. Every August site and every September site had a match in the other edition.

ENWL, September 2026 edition to October 2026 edition, for this customer’s sites: 1 site matched. Every September site and every October site had a match in the other edition.

No change to any detail QueueWatch tracks for its sites so far.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?