Distribution / Sites / Customer

NETWORK RAIL INFRASTRUCTURE LIMITED

Customer named in the DNOs' registers

In SSEN's September 2026 and ENWL's September 2026 editions

The registers spell this customer’s name more than one way: “NETWORK RAIL INFRASTRUCTURE LIMITED” (6 sites) and “NETWORK RAIL INFRASTRUCTURE LTD” (1 site).

7sites of 1 MW and over
27.5 MWcapacity
27.5 MWconnected (7 sites)
–accepted to connect (0 sites)

Capacity by DNO

DNOEditionSitesCapacityConnectedAccepted to connect
SSENSeptember 2026 edition19.5 MW9.5 MW–
ENWLSeptember 2026 edition618 MW18 MW–

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Gas and other fossil618 MW18 MW–
Other or not stated19.5 MW9.5 MW–

Each site is grouped by its first energy source, as the register names it.

Sites

Each site under this name in the DNOs' latest editions, the largest first.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

SiteDNOGrid supply pointTechnologyStatusMW
NORTH HYDE SUB STNSSENNORTH HYDE GSPOther or not statedConnected9.5
KINGSWAY BUSINESS PARKENWLHARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUPGas and other fossilConnected4
JOHN MILNE AVENUEENWLHARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUPGas and other fossilConnected3
PARKSIDE RAILWAY STATIONENWLSPEN - OUT OF AREAGas and other fossilConnected3
RAY LANEENWLPENWORTHAM EAST GSP / ROCHDALE SGT 1 GROUPGas and other fossilConnected3
STYAL ROADENWLSOUTH MANCHESTER GSPGas and other fossilConnected3
EDGELEY RAILWAY STATIONENWLBREDBURY GSPGas and other fossilConnected2

Grid supply points

Each grid supply point its sites are at, with the capacity of its own sites there.

Grid supply pointDNOSitesConnectedAccepted to connect
NORTH HYDE GSPSSEN19.5 MW–
HARKER ENWL SGTS 1 2 3A 4 / HUTTON GSP GROUPENWL27 MW–
PENWORTHAM EAST GSP / ROCHDALE SGT 1 GROUPENWL13 MW–
SOUTH MANCHESTER GSPENWL13 MW–
SPEN - OUT OF AREAENWL13 MW–
BREDBURY GSPENWL12 MW–

What changed recently

Changes to its sites found in both of two consecutive monthly editions of their DNO's register, the latest first.

SSEN, August 2026 edition to September 2026 edition, for this customer's sites: 1 site matched. Every August site and every September site had a match in the other edition.

ENWL, May 2026 edition to September 2026 edition, for this customer's sites: 6 sites matched. Every May site and every September site had a match in the other edition.

No change to the status, capacity, technology or customer of its sites in the editions QueueWatch holds.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose