Bowsheil Solar and Battery
- Connection date
- 31 Oct 2031
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage + Solar
- Total capacity
- 167 MW
- Connected now
- 0 MW
- Still to connect
- 167 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-002662
- In the register since
- March 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Awaiting Consents
- 24 Dec 2024 registerConnection date moved from 2 May 2030 to 31 Oct 2031 (+18 months)
- 26 Mar 2024 registerAdded to the register
Also at Bowsheils 132kV Substation
Substation viewNo other projects in the register at this connection point.