London North East Connection Node A 400kV
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Waltham Cross Farm 2 | Waltham Cross 7 Renewables Limited | Storage with solar or wind | 700 | 4 Apr 2033 | Not stated | Scoping |
| Waltham Cross BESS | SHAW-ENERGI LTD | Storage | 300 | 31 Oct 2033 | Gate 1 | Scoping |
Recent changes
- Waltham Cross Farm 2England and Wales, Storage with solar or windRestructured from 1 stage (700 MW from 4 Apr 2033) to 1 stage (700 MW from 4 Apr 2033)
- Waltham Cross Farm 2England and Wales, Storage with solar or windConnection point changed from Waltham Cross B 400kV Substation to London North East Connection Node A 400kV
- Waltham Cross BESSEngland and Wales, StorageConnection point changed from Waltham Cross 400kV Substation to London North East Connection Node A 400kV
- Waltham Cross BESSEngland and Wales, StorageMarked as Gate 1
- Waltham Cross Farm 2England and Wales, Storage with solar or windStage removed (700 MW from 30 Nov 2033)
- Waltham Cross Farm 2England and Wales, Storage with solar or windRestructured from 1 stage (700 MW from 4 Apr 2033) to 2 stages (700 MW from 4 Apr 2033, 700 MW from 30 Nov 2033)
- Waltham Cross Farm 2England and Wales, Storage with solar or windAdded to the registerNew
- Waltham Cross BESSEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?