Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Invenergy Development UK Ltd

Customer named in the TEC register

7projects in the register
1.3 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
CaorachCaorach 132 KV SubstationStorage with solar or wind8131 Oct 2033Gate 1Scoping
Creag Dhubh WindfarmCreag Dhubh Wind Farm and BESS 132kV SubstationStorage with solar or wind17131 Oct 2033Gate 1Scoping
Mid HillMid Hill 132kV SubstationStorage with solar or wind22830 Oct 2034Gate 1Scoping
CliffhopeTeviot 400/132kV SubstationStorage with solar or wind20531 Oct 2034Gate 1Scoping
KnarieNarie 400/132kV SubstationStorage with solar or wind29731 Oct 2036Gate 1Awaiting Consents
Craiglarie Wind FarmLadyburn 132kV SubstationStorage with solar or wind17031 Oct 2037Not statedScoping
Tioram Wind FarmNEW CARRADALE 132KV SUBSTATIONOnshore wind16031 Oct 2037Gate 1Scoping

Recent changes

  • Mid HillSouth Scotland, Storage with solar or windConnection date moved from 31 Oct 2034 to 30 Oct 2034 (1 day earlier)
  • Mid HillSouth Scotland, Storage with solar or windConnection date moved from 30 Oct 2034 to 31 Oct 2034 (1 day later)
  • Tioram Wind FarmNorth Scotland, Onshore windConnection point changed from CARRADALE 3 GSP to NEW CARRADALE 132KV SUBSTATION
  • Tioram Wind FarmNorth Scotland, Onshore windMarked as Gate 1
  • CaorachNorth Scotland, Storage with solar or windMarked as Gate 1
  • Mid HillSouth Scotland, Storage with solar or windMarked as Gate 1
  • KnarieSouth Scotland, Storage with solar or windMarked as Gate 1
  • Creag Dhubh WindfarmNorth Scotland, Storage with solar or windMarked as Gate 1
  • KnarieSouth Scotland, Storage with solar or windRenamed from Narie
  • CliffhopeSouth Scotland, Storage with solar or windMarked as Gate 1
  • CliffhopeSouth Scotland, Storage with solar or windConnection point changed from Hawick 132kV Substation to Teviot 400/132kV Substation
  • KnarieSouth Scotland, Storage with solar or windConnection point changed from Glenlee 132/11kV to Narie 400/132kV Substation
  • Mid HillSouth Scotland, Storage with solar or windConnection point changed from Hawick 132kV Substation to Mid Hill 132kV Substation
  • Craiglarie Wind FarmSouth Scotland, Storage with solar or windAdded to the registerNew
  • Tioram Wind FarmNorth Scotland, Onshore windAdded to the registerNew
  • CaorachNorth Scotland, Storage with solar or windAdded to the registerNew
  • CliffhopeSouth Scotland, Storage with solar or windAdded to the registerNew
  • Creag Dhubh WindfarmNorth Scotland, Storage with solar or windAdded to the registerNew
  • KnarieSouth Scotland, Storage with solar or windConnection date moved from 31 Oct 2035 to 31 Oct 2036 (+12 months)+12 mo
  • Mid HillSouth Scotland, Storage with solar or windAdded to the registerNew
  • KnarieSouth Scotland, Storage with solar or windSubstation name updated in the register (from Glenlee GSP to Glenlee 132/11kV)
  • KnarieSouth Scotland, Storage with solar or windRenamed from Knarie
  • KnarieSouth Scotland, Storage with solar or windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO