- Connection date
- 31 Oct 2036
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage + Onshore wind
- Total capacity
- 297 MW
- Connected now
- 0 MW
- Still to connect
- 297 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-004048
- In the register since
- April 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 21 Apr 2026 registerMarked as Gate 1
- 19 Dec 2025 registerRenamed from Narie
- 29 Aug 2025 registerConnection point changed from Glenlee 132/11kV to Narie 400/132kV Substation
- 28 Mar 2025 registerConnection date moved from 31 Oct 2035 to 31 Oct 2036 (+12 months)
- 27 Sep 2024 registerSubstation name updated in the register (from Glenlee GSP to Glenlee 132/11kV)
- 30 Jul 2024 registerRenamed from Knarie
- 26 Apr 2024 registerAdded to the register
Also at Narie 400/132kV Substation
Substation viewNo other projects in the register at this connection point.