Tioram Wind Farm
Invenergy Development UK Ltd at NEW CARRADALE 132KV SUBSTATION
- Connection date
- 31 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 160 MW
- Connected now
- 0 MW
- Still to connect
- 160 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-005973
- In the register since
- June 2025
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Jun 2026 registerConnection point changed from CARRADALE 3 GSP to NEW CARRADALE 132KV SUBSTATION
- 16 Jun 2026 registerMarked as Gate 1
- 27 Jun 2025 registerAdded to the register
Also at NEW CARRADALE 132KV SUBSTATION
Substation viewNo other projects in the register at this connection point.