- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 205 MW
- Connected now
- 0 MW
- Still to connect
- 205 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-006052
- In the register since
- March 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 9 Dec 2025 registerMarked as Gate 1
- 29 Aug 2025 registerConnection point changed from Hawick 132kV Substation to Teviot 400/132kV Substation
- 28 Mar 2025 registerAdded to the register
Also at Teviot 400/132kV Substation
Substation view2 other projects, 808 MW still to connect at this substation in total. 603 MW is due to connect here before this project’s connection date of 31 Oct 2034.