Pembroke 132kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Erebus | Blue Gem Wind Limited | Offshore wind | 95.3 | 26 Jul 2028 | Not stated | Scoping |
| Pembroke (spare bay) | Pembroke Green Limited | Storage | 120 | 30 Jul 2028 | Not stated | Consents Approved |
Recent changes
- Pembroke (spare bay)England and Wales, StorageCustomer changed from ENSO GREEN HOLDINGS LIMITED to Pembroke Green Limited
- Pembroke (spare bay)England and Wales, StorageConnection date moved from 30 Oct 2026 to 30 Jul 2028 (+21 months)+21 mo
- Pembroke (spare bay)England and Wales, StorageStatus changed from Scoping to Consents Approved
- Pembroke (spare bay)England and Wales, StorageTechnology changed from Storage, Solar to Storage
- ErebusEngland and Wales, Offshore windCapacity changed from 91 MW to 95.3 MW
- ErebusEngland and Wales, Offshore windConnection date moved from 2 Nov 2026 to 26 Jul 2028 (+21 months)+21 mo
- ErebusEngland and Wales, Offshore windSubstation name updated in the register (from Pembroke 132kV to Pembroke 132kV Substation)
- Pembroke (spare bay)England and Wales, StorageSubstation name updated in the register (from Pembroke 132kV to Pembroke 132kV Substation)
- Pembroke (spare bay)England and Wales, StorageAdded to the registerNew
- ErebusEngland and Wales, Offshore windConnection date moved from 11 Feb 2026 to 2 Nov 2026 (+9 months)+9 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?