Tewitt Farm BESS
Apatura Battery Ltd at Leeds North Connection Node D 400kV Substation
- Connection date
- 30 Oct 2035
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003917
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 7 Apr 2026 registerMarked as Gate 1
- 31 Jan 2025 registerConnection point changed from Bradford West GSP to Leeds North Connection Node D 400kV Substation
- 24 Dec 2024 registerConnection date moved from 31 Oct 2035 to 30 Oct 2035 (1 day earlier)
- 29 Oct 2024 registerConnection date moved from 31 Oct 2037 to 31 Oct 2035 (−24 months)
- 28 Jun 2024 registerCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
- 30 Jan 2024 registerAdded to the register
Also at Leeds North Connection Node D 400kV Substation
Substation view1 other project, 450 MW still to connect at this substation in total.