Wymondley 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Wymondley | Priory Generation Limited | Storage with solar or wind | 57 | 30 May 2027 +19 mo | Gate 2 | Consents Approved |
| Wymondley | ENSO GREEN HOLDINGS LIMITED | Storage with solar or wind | 400 | 31 Oct 2032 | Gate 1 | Scoping |
| Wymondley High Impact Green Energy Hub (HIGEH) 1 | TELIS ENERGY UK LIMITED | Storage with solar or wind | 1,000 | 31 Oct 2033 | Not stated | Scoping |
| Wymondley BESS Limited | AGR RENEWABLES LIMITED | Storage | 35.5 | 31 Oct 2034 | Not stated | Awaiting Consents |
Recent changes
- WymondleyEngland and Wales, Storage with solar or windStatus changed from Awaiting Consents to Consents Approved
- WymondleyEngland and Wales, Storage with solar or windGiven a Gate 2 connection offerGate 2
- WymondleyEngland and Wales, Storage with solar or windConnection date moved from 30 Jan 2032 to 31 Oct 2032 (+9 months)+9 mo
- WymondleyEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2032 to 30 Jan 2032 (−9 months)−9 mo
- WymondleyEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2025 to 30 May 2027 (+19 months)+19 mo
- Wymondley BESS LimitedEngland and Wales, StorageStatus changed from Scoping to Awaiting Consents
- WymondleyEngland and Wales, Storage with solar or windMarked as Gate 1
- WymondleyEngland and Wales, Storage with solar or windTechnology changed from Storage to Storage, Solar
- WymondleyEngland and Wales, Storage with solar or windCustomer changed from PIVOTED POWER LLP to Priory Generation Limited
- WymondleyEngland and Wales, Storage with solar or windRestructured from 3 stages (200 MW from 31 Oct 2031, 100 MW from 31 Oct 2032, 100 MW from 31 Oct 2033) to 1 stage (400 MW from 31 Oct 2032). First connection date +12 months+12 mo
- Wymondley High Impact Green Energy Hub (HIGEH) 1England and Wales, Storage with solar or windConnection point changed from Wymondley 2 400kV Substation to Wymondley 400kV Substation
- WymondleyEngland and Wales, Storage with solar or windConnection date moved from 30 Jun 2025 to 31 Oct 2025 (+4 months)+4 mo
- Wymondley BESS LimitedEngland and Wales, StorageConnection date moved from 31 Oct 2031 to 31 Oct 2034 (+36 months)+36 mo
- Wymondley High Impact Green Energy Hub (HIGEH) 1England and Wales, Storage with solar or windStatus changed from Awaiting Consents to Scoping
- Wymondley BESS LimitedEngland and Wales, StorageAdded to the registerNew
- Wymondley High Impact Green Energy Hub (HIGEH) 1England and Wales, Storage with solar or windConnection point changed from Eaton Socon GSP to Wymondley 2 400kV Substation
- Wymondley High Impact Green Energy Hub (HIGEH) 1England and Wales, Storage with solar or windAdded to the registerNew
- WymondleyEngland and Wales, Storage with solar or windSubstation name updated in the register (from Wymondley 400kV to Wymondley 400kV Substation)
- WymondleyEngland and Wales, Storage with solar or windCapacity changed from 49.9 MW to 57 MW
- WymondleyEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2022 to 30 Jun 2025 (+32 months)+32 mo
- WymondleyEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?