Wymondley High Impact Green Energy Hub (HIGEH) 1
- Connection date
- 31 Oct 2033
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar + Reactive compensation + Onshore wind
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002659
- In the register since
- July 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jun 2025 registerConnection point changed from Wymondley 2 400kV Substation to Wymondley 400kV Substation
- 27 Feb 2024 registerStatus changed from Awaiting Consents to Scoping
- 29 Aug 2023 registerConnection point changed from Eaton Socon GSP to Wymondley 2 400kV Substation
- 28 Jul 2023 registerAdded to the register
Also at Wymondley 400kV Substation
Substation view3 other projects, 1.5 GW still to connect at this substation in total. 457 MW is due to connect here before this project’s connection date of 31 Oct 2033.