Wymondley BESS Limited
- Connection date
- 31 Oct 2034
- Gate
- Not stated
- Status
- Awaiting Consents
- Planning consent
- Granted by the Secretary of State 11 Mar 2024
North Hertfordshire, reference 21/03380/FP · Source: REPD - Technology
- Storage
- Total capacity
- 35.5 MW
- Connected now
- 0 MW
- Still to connect
- 35.5 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003496
- In the register since
- October 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Awaiting Consents
- 24 Dec 2024 registerConnection date moved from 31 Oct 2031 to 31 Oct 2034 (+36 months)
- 31 Oct 2023 registerAdded to the register
Also at Wymondley 400kV Substation
Substation view3 other projects, 1.5 GW still to connect at this substation in total. 1.5 GW is due to connect here before this project’s connection date of 31 Oct 2034.