Noventum Market Harborough
NOVENTUM POWER SOLAR 1 LIMITED at West Anglia Connection Node F 400kV Substation
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 249 MW
- Connected now
- 0 MW
- Still to connect
- 249 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003759
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 May 2026 registerMarked as Gate 1
- 27 Aug 2024 registerConnection point changed from Market Harborough 400kV Substation to West Anglia Connection Node F 400kV Substation
- 27 Aug 2024 registerConnection date moved from 31 Oct 2031 to 31 Oct 2034 (+36 months)
- 30 Jan 2024 registerAdded to the register
Also at West Anglia Connection Node F 400kV Substation
Substation view5 other projects, 3.4 GW still to connect at this substation in total.
- Lightsource BraybrookeLightsource Renewable UK Development Limited, Storage with solar or wind, Gate 1Oct 2034240 MW
- Little HarrowdenLittle Harrowden 10 Renewables Limited, Solar, Not statedOct 20341 GW
- Market HarboroughCONNECTID 1 LIMITED, Storage with solar or wind, Not statedOct 2034700 MW
- Market Harborough Green Energy HubTELIS ENERGY UK LIMITED, Multi-technology hub, Gate 1Oct 20341 GW
- Nethercourt Solar & BESS FarmGreentech Invest UK (15) Limited, Storage with solar or wind, Gate 1Oct 2034240 MW