Warwickshire Connection Node A 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Bellbroughton Energy Park | ELGIN ENERGY ES CO LIMITED | Storage with solar or wind | 500 | 30 Oct 2037 | Gate 1 | Scoping |
| Dunclent Battery Storage | Firma Vogt Solar Ltd | Storage | 400 | 30 Oct 2037 | Gate 1 | Scoping |
| Mount Pleasant | HARMONY ENERGY LIMITED | Storage | 200 | 31 Oct 2037 | Gate 1 | Scoping |
Recent changes
- Bellbroughton Energy ParkEngland and Wales, Storage with solar or windMarked as Gate 1
- Mount PleasantEngland and Wales, StorageMarked as Gate 1
- Mount PleasantEngland and Wales, StorageConnection point changed from Bishops Wood 275kV Substation to Warwickshire Connection Node A 400kV Substation
- Dunclent Battery StorageEngland and Wales, StorageMarked as Gate 1
- Bellbroughton Energy ParkEngland and Wales, Storage with solar or windCustomer changed from Elgin Energy Holdings Limited to ELGIN ENERGY ES CO LIMITED
- Bellbroughton Energy ParkEngland and Wales, Storage with solar or windCustomer changed from ELGIN ENERGY ES CO LIMITED to Elgin Energy Holdings Limited
- Mount PleasantEngland and Wales, StorageAdded to the registerNew
- Bellbroughton Energy ParkEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2027 to 30 Oct 2037 (+120 months)+120 mo
- Dunclent Battery StorageEngland and Wales, StorageConnection date moved from 31 Oct 2030 to 30 Oct 2037 (+84 months)+84 mo
- Dunclent Battery StorageEngland and Wales, StorageConnection point changed from Dunclent 400kV to Warwickshire Connection Node A 400kV Substation
- Bellbroughton Energy ParkEngland and Wales, Storage with solar or windConnection point changed from Bellbroughton 275kV Energy Park to Warwickshire Connection Node A 400kV Substation
- Bellbroughton Energy ParkEngland and Wales, Storage with solar or windAdded to the registerNew
- Dunclent Battery StorageEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose