Dunclent Battery Storage
Firma Vogt Solar Ltd at Warwickshire Connection Node A 400kV Substation
- Connection date
- 30 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002827
- In the register since
- July 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 13 Mar 2026 registerMarked as Gate 1
- 24 Dec 2024 registerConnection date moved from 31 Oct 2030 to 30 Oct 2037 (+84 months)
- 26 Nov 2024 registerConnection point changed from Dunclent 400kV to Warwickshire Connection Node A 400kV Substation
- 28 Jul 2023 registerAdded to the register
Also at Warwickshire Connection Node A 400kV Substation
Substation view2 other projects, 1.1 GW still to connect at this substation in total.